Construction projects involving the University of Arkansas require unique considerations
to ensure the safety of students and the protection of campus resources, setting them
apart from typical construction efforts.
List the project name in the subject line of the email.
Only one project per email
After Hours Emergencies
In the event of an after-hours emergency or if you witness a leak, power outage, etc.
not related to your construction project, please report the problem by calling 575-5050
(between 7:30- 5:00 M-F) or 575-2222 (after hours). On-call Facilities Management
employees will attend to the issue.
Parking on Campus
Parking on campus is a challenge and requires advanced planning. When developing your
site plan for review, identify any parking spaces required for dumpsters, lay down,
or access to the project. Provide the Construction Coordinator with a map clearly
identifying these spaces and duration needed. Depending on the time of year and location
of the project, the number of parking permits allowed for the JOC and subcontractors
will vary. Work through the Construction Coordinator for approval, then purchase permits
through the Transit and Parking Department located at 155 S. Razorback Rd. Their phone
number is 479-575-PARK or you may email them at parking@uark.edu.
Prior to Site Mobilization
Once the Letter of Intent has been issued, we will need to review the Site Mobilization
Plan. This plan must show the following:
Location of site fence, main gates, and vehicular site access
Pedestrian safety plan if detours are required, show detour and signage locations
for wayfinding
Location of portable toilets
Location of dumpster if required
Identify BMP's required and inlets that will need protection. If the site is less
than one acre, a formal NPDES Small Site Permit is not required, but Storm Water Management is always required by the contractor. Review implemented BMP's prior to soil disturbance.
Pre-Con Agenda
In addition to a review of University Policies (Tobacco Free Campus, Expectations
of Behavior by Subcontractors, Parking Requirements, Tree Protection, etc.) be prepared
for the following:
Review of the project schedule
Identification of utility outages
Timing within schedule, duration, and what will be affected by the outage
Identification of street closures or parking spaces that will be needed to accomplish
the work
Contractor Key Policy
The Contractor Key Policy applies to low bid, alt delivery, JOC task orders, and IDIQ
task orders when contracted directly with FAMA and retention of payment is held to
secure return of keys.
Whenever practical, construction cores shall be used for contractor controlled construction
areas.
The project’s Key Accountability Form shall be attached to the initial Letter of Intent (LOI) for the project and filled
out by the construction coordinator authorizing issuance of the keys anticipated for
the project.
NOTE: TheKey Accountability Form shall be attached to the LOI whether or not any keys are expected to be issued for
the work and the contractor must return the form, signed by the Key Office, with the
final pay application even if no keys were issued.
The contractor is not required to check out all the keys on the form if they are not
required. Additional keys may be added to the form throughout the project if the need
arises.
The Key Office at 1486 Mitchell Street to complete the key sign out process and issue the requested
keys.
Restricted keys require Director approval prior to release. Restricted keys include
roofs, high voltage, tunnels, and elevators.
The contractor shall initial and date the Key Accountability Form when the keys are received and provide a copy to the coordinator.
Keys will only be issued to employees of the general contractor. It is the general
contractor’s responsibility to maintain accountability and key control if they choose
to loan keys to any subcontractor. Subcontractors may NOT directly check out keys.
Keys shall NOT be duplicated.
No deposit shall be charged for checking out a key. However, sufficient retainage
shall be held and final payment shall not be released until the project’s Key Accountability Form is signed off by the Key Office and any required fees for late or lost keys have
been paid.
The required return date of all keys issued for the contract is 60 days after the
project substantial completion date, unless an extension is approved by the coordinator,
or whenever final payment is requested, whichever is sooner.
In no case shall keys be issued for longer than 1 year without verifying accountability,
in person, to confirm the contractor still maintains possession of the key(s).
The Key Accountability Form does not need to be updated until completion of the project, however, the contractor
must renew the keys after 1 year with the key office.
It is solely the contractor’s responsibility, not the coordinator and nor the Key
Office’s, to track the required renewal dates and renew the keys after 1 year. Keys
renewed more than 30 days late (whether at annual renewal or upon project completion)
will incur a flat $125 fee per key for each 30 days they are late.
Example: 28 days late: No Fee. 45 days late: $125 per key. 75 days late: $250 per
key.
Any employee of the general contractor may renew the keys with identification.
Lost keys will incur the charge established at key checkout and determined by the
Key Office. Charges for lost keys vary depending on the type of key.
Should the contractor fail to pay the required fees, they shall be deducted from the
project’s final pay application.
City and Campus Impacts
Street and Lane Closure Requests
City street closures on campus require UA approval prior to submission to the City of Fayetteville. When requesting a street closure, provide
your Construction Coordinator with an aerial map that includes the location of the
closure and identifies how traffic will be rerouted in the area. Information to include
in this submission:
Dates of closure (duration)
Locations of signage
Pedestrian safety plan
Once the plan closure (or detour) is approved through the Construction Coordinator,
please copy the Coordinator on all correspondence with the City of Fayetteville.
SWPP on Campus
All projects on campus which require the disturbance of soil require BMP's to be in
place. Protection of inlets and containment of the storm water runoff is required.
The University is its own MS4 and issues NPDES Small Site permits for projects between 1 and 5 acres under the
University of Arkansas MS4 Permit from ADEQ.
Illicit Discharge Permit Requirements
Provide the following information to the Construction Coordinator two weeks prior
to draining or flushing Chilled or Heating Water Lines, or any other activity requiring
an Illicit Discharge Permit. Notification to the City of Fayetteville is required
if over 500 gallons are being released into the Sanitary Sewer System. If 1,000 gallons
or more are being discharged, a permit is required. The Construction Coordinator will
obtain the permit.
Approximate amount of water to be discharged in gallons
Cutsheet for chemicals and/or cleaner in the water
Time period for draining/flushing
If flushing continues beyond stated permit date, request an extension through the
Construction Coordinator.
project checklists
JOC/IDIQ Proposal Checklist
Proposal letter addressed to the Construction Coordinator, including the following:
Reference to the date of drawings priced or meeting when the scope was established
if there is no Design Professional
Cost summary, breaking out scope
Summary of scope
Exclusions and clarifications
Deductive/Add alternates requested (this will greatly speed up the decision processes)
This letter should be modified to the agreed upon contract amount noting all VE's
accepted or scope excluded.
Proposed schedule, start date, and duration.
Spreadsheet with Bidders list INCLUDING License Numbers, Bid amounts, and Non-Responsive
Bidders noted. A minimum of three bidders per trade are required.
Back up documentation of Low Bidders, sub-contractor proposal
RS Means pricing for self-performed work
Contract Checklist
One (1) copy of the following must be returned to the University before a contract can be processed through the University of Arkansas' accounting system.
Include the project name exactly how it is stated in the Letter of Intent
Proposal Letter addressed to the construction coordinator, including the following:
"This letter should be revised to the agreed upon contract amount noting all VE's
accepted or scope excluded."
Pricing Back-up
Agreement form - be sure to use the form provided by FAMA
Performance Payment Bond on projects over $50,000 (see Vendor Forms below)
Certificate of Insurance/Power of Attorney
The Certificate of Insurance shall name the Certificate Holder as “Board of Trustees
of the University of Arkansas” addressed FAMA, 521 South Razorback Road, Fayetteville,
AR 72701.
Grant Disclosure Form (Governor Executive Order 98-04) for GC (subs can be listed
later)
Change Order Documents Checklist
One (1) copy of the following mustbe returned to the University before a contract can be processed through the University of Arkansas' accounting system.
UA Change Order Form signed (inked signature) by GC and Design Consultant
Backup documentation for Change Order (C.O.) pricing
Pricing must be broken down for each C.O. request included and each C.O.R fully loaded
Amended Performance Payment Bond
Grant Disclosure Form for all new sub-contractors with more than $25,000.00 after the C.O.
FAMA Operational Notices & Reports
Provide Notice to FAMA project manager before any scheduled inspection as follows:
Immediate notice when State Inspectors (Plumbing, Health,Elevator, etc) are on site or expected.
Tap and Meter Notice - 2 week lead
Notice before scheduled inspections - 1 week lead
Rough-Ins of MEP and Fire
Pre Close-Up (before wall and ceiling finishes are installed)
Hood Testing
Finals on MEP, Fire, Building, ADA
Submit one (1) copy of each inspection report when readily available.
Emission Producing Equipment - submit EPE Form after submittals are approved by Architect
Backflow Preventer Test Reports - required before occupancy
Close Out Documents Checklist
Close-Outs (one digital copy) must be submitted for review prior to the Final Pay App; allow 2-3 weeks for review of Close Out documents.
Warranty letter for one year on all labor and materials from the GC
One (1) copy of the signed Pay Application must be submitted to cons@uark.edu.
Include the university-assigned PR number and the PO number.
List all approved Change Orders for the billing. If a Change Order is listed on the Pay App that has
not been processed, the Pay App cannot be paid.
Include an updated project schedule.
Include the Continuation Sheet / Schedule of Values.
Payment requests including stored materials must include backup documentation:
Inspection Report: The General Contractor shall inspect Stored Material and record the inspection date,
location, quantities of materials, and digital photos confirming the materials are
segregated from other materials in the facility and have been clearly labeled/identified
as belonging to the UA project.
Evidence of Insurance listing “Board of Trustees of the University of Arkansas” as
additional insured and loss payee:
Property Insurance certificate covering the bonded warehouse/location and the stored
materials.
Insurance certificate covering in-transit materials being delivered to the site.
Final Pay Request Documents Checklist
One (1) copy of the following must be returned to the University before a project can be closed-out and the final payment can be processed through the University
of Arkansas' accounting system.
Pay App Signed (inked signature) by the GC certifying payment, design professional
if required, and listing allapprovedChange Orders billed for.
Contractors Affidavit of Release of Liens
Warranty letter for one year on all labor and materials from the GC
Consent of Surety for Final Payment
Insurance Form (Power of Attorney documents)
Close-Outs must be submitted (one digital copy)
Allow 2-3 weeks for review of Close Out documents
Turn in Close Out documents for review prior to the final Pay App
Turn in keys to the Key Office
Submit signed key return form to the Construction Coordinator even if no keys were
issued for the project.
UA6-N-1 Form
The UA6-N-1 Invoice Form (revised 2023) is the required Professional Service Invoice and shall be used by
all architects, engineers, or on-call professionals.